友情链接: 今日新闻 新闻头条 百姓故事 通辽市新闻网 葡京21点 葡京手机投注 葡京投注 葡京下注 葡京网投 网上葡京 线上葡京 葡京充值 葡京快速充值 葡京快速充值中心 葡京视讯直播 葡京视频直播 葡京体育 葡京正网 葡京AG 葡京BBIN 葡京贵宾厅 葡京VIP厅 葡京捕鱼达人 葡京优惠活动 葡京在线客服 葡京真人视讯 葡京免费开户 葡京免费注册 葡京如何存款 葡京如何取款 葡京MG 葡京糖果派对 葡京连环夺宝 葡京斗鸡游戏 葡京幸运转盘 葡京轮盘 葡京老虎机 葡京游戏大厅 葡京AG电子 葡京MG电子 葡京PT电子 葡京皇冠体育 葡京沙巴体育 葡京电竞 葡京欢乐棋牌 葡京乐游棋牌 葡京开元棋牌 葡京真人娱乐 葡京捕鱼游戏 葡京网络游戏 葡京水果拉霸 葡京古怪猴子 葡京APP 葡京手机APP
TheDorraGroup - Home
Call Us  16077
Log In
About
About

A Contemporary state of the art business hub located in the heart of Sheikh Zayed city that will redefine the concept of administrative and commercial venues in Egypt. The Courtyard is located within a premium commercial zone at the Sheikh Zayed city, surrounded by residential suburbs and standing landmarks.  The Courtyard has been located only 20 minutes from the heart of Cairo through trouble free access points to and from downtown Cairo.

The Courtyard a daily unique experience of pleasure
The different exquisite ornamented clusters of buildings and the enchanting landscaping of luscious greenery will provide eye watering views and desirable vistas whether from your work space or below at the promenade. Adorned with features such as water fountains and illuminated walkways at sundown, the inviting ambiance of the Courtyard will set the stage of a new attraction in Sheikh Zayed.

Construction updates

Building A D B E C F H G K J
Earth Works
Excavation Works
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
Replacement Soil Works
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
Plain Concrete Works
Foundations Plain Concrete
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
Reinforced Concrete
R.C. for Foundations
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
R.C. for basement floor columns
 
 
100 %
100 %
100 %
100 %
100 %
100 %
 
 
R.C. for ground floor columns
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
R.C. for ground floor roof
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
R.C. for first floor columns
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
R.C. for first floor roof
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
R.C. for second floor columns
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
R.C. for second floor roof
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
100 %
60 %
R.C. for basement floor roof
 
 
100 %
100 %
100 %
100 %
100 %
100 %
 
 
Brick Works
Ground floor bricks
100 %
100 %
100 %
100 %
100 %
100 %
100 %
20 %
 
 
First floor bricks
100 %
100 %
100 %
100 %
100 %
100 %
100 %
20 %
 
 
Second floor bricks
100 %
100 %
100 %
100 %
100 %
100 %
100 %
20 %
 
 
Internal Plastering
Ground floor Plastering
100 %
100 %
100 %
100 %
100 %
100 %
100 %
 
 
 
First floor Plastering
100 %
100 %
100 %
100 %
100 %
100 %
100 %
 
 
 
Second floor Plastering
100 %
100 %
100 %
100 %
100 %
100 %
90 %